CLADTECH-LOGOCLADDING TECHNOLOGY SHANXI CO., LTD
CLADDING TECHNOLOGY SHANXI CO., LTD
CLADDING · BIMETAL PRODUCT · BIMETAL PRESSURE VESSEL TECHNICAL STUDY

Pre-Placed Additional Filler Metal Plate Submerged Arc Cladding

Literature Overview and Technical Context

This 1997 study by Rao Linping from Jinan Xinli Water Supply Equipment Co., Ltd. describes an innovative submerged arc cladding technique utilizing pre-placed additional filler metal plates. This approach represents a departure from conventional wire-fed or strip-fed submerged arc cladding by introducing a pre-positioned solid metal plate as the primary filler source, with a submerged arc serving as the bonding energy source. The application context—water supply equipment manufacturing—suggests the need for corrosion-resistant surface layers on carbon steel pressure vessels or pipe components intended for water service.

The technique is particularly relevant for producing bimetallic components where the cladding layer thickness exceeds what can be practically achieved with conventional wire or strip feeding, and where the geometry allows for pre-positioning of the filler plate.

Technical Principle and Process Description

Process Configuration

The pre-placed plate method operates on the following principle:

  1. A filler metal plate of the desired cladding composition is positioned on the prepared substrate surface
  2. The substrate is preheated to promote fusion
  3. A submerged arc is directed along the interface between the substrate and the pre-placed plate
  4. The arc melts the interface, bonding the plate to the substrate
  5. Multiple plates may be placed sequentially to build up the required thickness

Process Parameters

Parameter Typical Value Impact
Substrate material Q235B / Q345B Carbon steel base
Filler plate material 06Cr19Ni10 (304) or 06Cr17Ni12Mo2 (316) Corrosion resistance
Plate thickness 3-6 mm per plate Build-up rate
Number of plates 1-3 plates Total cladding thickness
Arc current 500-700 A Fusion depth
Arc voltage 28-35 V Penetration profile
Travel speed 100-200 mm/min Bonding quality
Flux type RZ-501 or similar Slag protection
Preheat temperature 150-250°C Prevent cracking
Interpass temperature <250°C Control cooling rate

Metallurgical Analysis of the Bond Interface

Interface Structure

The bond interface in pre-placed plate cladding exhibits a unique microstructure compared to wire-fed or strip-fed methods:

Zone Location Microstructure Hardness
Substrate HAZ Base metal near interface Coarse grain, possible phase transformation 150-200 HV
Fusion zone Melted interface region Columnar grains, mixed composition 200-280 HV
Dilution zone Within filler plate Gradient composition 180-220 HV
Unaffected filler Beyond dilution zone Original filler microstructure 180-200 HV

The key metallurgical concern is the dilution zone within the filler plate. If the arc penetration is too deep, excessive substrate metal mixes into the filler, degrading the corrosion resistance of the cladding layer. The dilution rate in the fusion zone can reach 30-50%, which is significantly higher than the dilution in the final surface layer of wire-fed cladding.

Dilution Control Strategies

Strategy Implementation Effectiveness
Multi-pass with reduced penetration Lower current, higher voltage Moderate reduction
Sequential plate placement Bond each plate separately Good reduction
Final surfacing pass Wire-fed overlay on final plate surface Excellent reduction
Reduced travel speed Slower welding for shallower penetration Limited benefit
Preheating optimization Higher preheat for reduced thermal gradient Moderate improvement

Quality Assessment and Performance Evaluation

Bond Strength Testing

Test Method Standard Reference Acceptance Criteria
Peel test GB/T 3323 >150 MPa
Shear test ASTM B671 >200 MPa
Macrographic examination Visual + metallography No cracks, no lack of fusion
Intergranular corrosion ASTM A923 <5% grain boundary attack
Salt spray test ASTM B117 No red rust at 1000 hours

Comparison with Conventional Methods

Parameter Pre-Placed Plate Wire-Fed SAW Strip Cladding
Build-up rate Very high High High
Layer thickness per pass 3-6 mm 3-8 mm 3-6 mm
Dilution control Moderate Good Excellent
Geometric flexibility Limited High Moderate
Cost efficiency High Moderate Low
Surface quality Requires machining Requires machining Requires machining
Applicable geometry Flat, large surfaces Any accessible Flat, large surfaces

Engineering Application and Practical Considerations

The pre-placed plate method is most suitable for:

For water supply equipment, this technique is particularly applicable to:

  1. Internal cladding of large-diameter water tanks
  2. Pipe fittings with flat surfaces suitable for plate placement
  3. Valve bodies requiring localized corrosion-resistant areas
  4. Pump casings with accessible flat surfaces

The technique requires careful attention to the sequence of plate placement and welding. The first plate must be positioned with precise alignment to the substrate edge, and subsequent plates must overlap the previously welded plate by 5-10 mm to ensure complete fusion bonding.

Study Insights and Implications

Rao Linping's 1997 work represents an innovative approach to achieving thick cladding layers with high build-up rates. While the method has inherent limitations in terms of dilution control and geometric flexibility, it offers a cost-effective solution for specific applications where these limitations are acceptable. The technique essentially transforms the submerged arc welding process from a deposition operation into a bonding operation, which changes the fundamental process physics and the associated quality considerations. For modern practitioners, this work demonstrates that creative adaptation of welding processes to new configurations can yield practical solutions that complement rather than replace conventional approaches, particularly in cost-sensitive manufacturing environments.