Pre-Placed Additional Filler Metal Plate Submerged Arc Cladding
Literature Overview and Technical Context
This 1997 study by Rao Linping from Jinan Xinli Water Supply Equipment Co., Ltd. describes an innovative submerged arc cladding technique utilizing pre-placed additional filler metal plates. This approach represents a departure from conventional wire-fed or strip-fed submerged arc cladding by introducing a pre-positioned solid metal plate as the primary filler source, with a submerged arc serving as the bonding energy source. The application context—water supply equipment manufacturing—suggests the need for corrosion-resistant surface layers on carbon steel pressure vessels or pipe components intended for water service.
The technique is particularly relevant for producing bimetallic components where the cladding layer thickness exceeds what can be practically achieved with conventional wire or strip feeding, and where the geometry allows for pre-positioning of the filler plate.
Technical Principle and Process Description
Process Configuration
The pre-placed plate method operates on the following principle:
- A filler metal plate of the desired cladding composition is positioned on the prepared substrate surface
- The substrate is preheated to promote fusion
- A submerged arc is directed along the interface between the substrate and the pre-placed plate
- The arc melts the interface, bonding the plate to the substrate
- Multiple plates may be placed sequentially to build up the required thickness
Process Parameters
| Parameter | Typical Value | Impact |
|---|---|---|
| Substrate material | Q235B / Q345B | Carbon steel base |
| Filler plate material | 06Cr19Ni10 (304) or 06Cr17Ni12Mo2 (316) | Corrosion resistance |
| Plate thickness | 3-6 mm per plate | Build-up rate |
| Number of plates | 1-3 plates | Total cladding thickness |
| Arc current | 500-700 A | Fusion depth |
| Arc voltage | 28-35 V | Penetration profile |
| Travel speed | 100-200 mm/min | Bonding quality |
| Flux type | RZ-501 or similar | Slag protection |
| Preheat temperature | 150-250°C | Prevent cracking |
| Interpass temperature | <250°C | Control cooling rate |
Metallurgical Analysis of the Bond Interface
Interface Structure
The bond interface in pre-placed plate cladding exhibits a unique microstructure compared to wire-fed or strip-fed methods:
| Zone | Location | Microstructure | Hardness |
|---|---|---|---|
| Substrate HAZ | Base metal near interface | Coarse grain, possible phase transformation | 150-200 HV |
| Fusion zone | Melted interface region | Columnar grains, mixed composition | 200-280 HV |
| Dilution zone | Within filler plate | Gradient composition | 180-220 HV |
| Unaffected filler | Beyond dilution zone | Original filler microstructure | 180-200 HV |
The key metallurgical concern is the dilution zone within the filler plate. If the arc penetration is too deep, excessive substrate metal mixes into the filler, degrading the corrosion resistance of the cladding layer. The dilution rate in the fusion zone can reach 30-50%, which is significantly higher than the dilution in the final surface layer of wire-fed cladding.
Dilution Control Strategies
| Strategy | Implementation | Effectiveness |
|---|---|---|
| Multi-pass with reduced penetration | Lower current, higher voltage | Moderate reduction |
| Sequential plate placement | Bond each plate separately | Good reduction |
| Final surfacing pass | Wire-fed overlay on final plate surface | Excellent reduction |
| Reduced travel speed | Slower welding for shallower penetration | Limited benefit |
| Preheating optimization | Higher preheat for reduced thermal gradient | Moderate improvement |
Quality Assessment and Performance Evaluation
Bond Strength Testing
| Test Method | Standard Reference | Acceptance Criteria |
|---|---|---|
| Peel test | GB/T 3323 | >150 MPa |
| Shear test | ASTM B671 | >200 MPa |
| Macrographic examination | Visual + metallography | No cracks, no lack of fusion |
| Intergranular corrosion | ASTM A923 | <5% grain boundary attack |
| Salt spray test | ASTM B117 | No red rust at 1000 hours |
Comparison with Conventional Methods
| Parameter | Pre-Placed Plate | Wire-Fed SAW | Strip Cladding |
|---|---|---|---|
| Build-up rate | Very high | High | High |
| Layer thickness per pass | 3-6 mm | 3-8 mm | 3-6 mm |
| Dilution control | Moderate | Good | Excellent |
| Geometric flexibility | Limited | High | Moderate |
| Cost efficiency | High | Moderate | Low |
| Surface quality | Requires machining | Requires machining | Requires machining |
| Applicable geometry | Flat, large surfaces | Any accessible | Flat, large surfaces |
Engineering Application and Practical Considerations
The pre-placed plate method is most suitable for:
- Large flat surfaces where the geometry permits plate placement
- Thick cladding layers (10-20 mm) where wire feeding would be impractical
- Applications where build-up rate is more important than dilution control
- Batch production where setup time can be amortized over multiple units
For water supply equipment, this technique is particularly applicable to:
- Internal cladding of large-diameter water tanks
- Pipe fittings with flat surfaces suitable for plate placement
- Valve bodies requiring localized corrosion-resistant areas
- Pump casings with accessible flat surfaces
The technique requires careful attention to the sequence of plate placement and welding. The first plate must be positioned with precise alignment to the substrate edge, and subsequent plates must overlap the previously welded plate by 5-10 mm to ensure complete fusion bonding.
Study Insights and Implications
Rao Linping's 1997 work represents an innovative approach to achieving thick cladding layers with high build-up rates. While the method has inherent limitations in terms of dilution control and geometric flexibility, it offers a cost-effective solution for specific applications where these limitations are acceptable. The technique essentially transforms the submerged arc welding process from a deposition operation into a bonding operation, which changes the fundamental process physics and the associated quality considerations. For modern practitioners, this work demonstrates that creative adaptation of welding processes to new configurations can yield practical solutions that complement rather than replace conventional approaches, particularly in cost-sensitive manufacturing environments.
CLADDING TECHNOLOGY SHANXI CO., LTD